Mitel 3rd Party Vendor - Toronto - Scheduled Maintenance

Scheduled Maintenance Report for Global Flex Status

Completed

The scheduled maintenance has been completed.
Posted Mar 26, 2025 - 08:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 26, 2025 - 00:00 UTC

Scheduled

Summary: Engineering will be performing maintenance on our networking infrastructure in the Toronto data center.

Customer Impact:During the maintenance window, customers may notice intermittent packet loss, site disconnects and/or increased latency while the maintenance is being performed.

Customer Action:All services will resume as normal at the end of the maintenance window. Customers are encouraged to validate connectivity within their environment.
Posted Mar 18, 2025 - 14:01 UTC
This scheduled maintenance affected: North America (Mitel Performance Analytics (FlexNA)).